Implementation of the second phase of the Smart Line plant

Author’s supervision is currently ongoing for the construction of a large-scale facility within the Vinnytsia Industrial Park.
Commissioned by Smart Line, our specialists are delivering a project for an industrial complex with a total area of approximately 8,000 m².
Key project parameters:
- Scale: The first phase (administrative and production building) has already been commissioned. Active work on the second phase is currently underway.
- Structural solutions: The project предусматриває an administrative and production building with a height of 25 metres. The frame is made of precast reinforced concrete produced locally, which helps optimize logistics and construction timelines.
- Engineering autonomy: A full комплекса of facilities required for the operation of the site has been designed, with integration into the industrial park’s utility networks.
- Environmental performance and logistics: The project includes local treatment facilities (domestic and stormwater drainage) as well as a well-planned transport layout for large vehicles.
Source: https://smart-line.in.ua/ua/

Other news
The TCH team has completed the development and implementation of a project to replace the absorption system in the extraction workshop of one of the leaders of Ukraine’s oil and fat industry — the American company BUNGE.
The new SPA complex for Mayak Resort has been successfully delivered based on the design developed by the company’s specialists, despite dense surrounding development and challenging hydrogeological conditions.
Today, children’s safety is the number one priority. TCH proves that a protective structure can be far more than just a concrete basement — it can be a high-tech, multifunctional space.
Construction of modern school shelters based on our designs is already underway in Brovary District, Kyiv Region.
Our team has completed the development of a complex reconstruction and expansion project for an industrial facility in the city of Vyshhorod. The client has obtained a construction permit, and project implementation has begun.